Schedule
-
Project Schedule
Environmental Assessment
- Public Information Centers: January 29 & 30, 2015
- Draft Environmental Assessment: May 2015
- Public Comment Period: June 2015
- Environmental Determination: July 2015
Construction*
- Preliminary Design (30%): July 2015
- Procurement and Design-Build Contract Award: 1st Qtr 2016
- Construction Complete: 4th Qtr 2018
*Tentative construction dates assuming that thereis a determination of no environmental impacts.