Depot lands continue to dog metro rail project

HMR officials have to deal with land acquisition, legal tangles and dredging of nala

Published - December 23, 2011 02:17 pm IST - Hyderabad:

inspection - Uppal casting yard for Hyderabad city pages.Photo: Special arrangement

inspection - Uppal casting yard for Hyderabad city pages.Photo: Special arrangement

Depot lands continue to dog the Hyderabad Metro Rail project.

Though most of the 100 acres at Nagole has been handed over to the L&T metro rail limited, the concessionaire building the project, there is still six acres of land occupied by marble shops which has to be taken over.

The earmarked 21 acre site for the Falaknuma depot is ready but the L&T has some issues about the topography and discussions are currently on sort it out.

Miyapur depot land of 100 acres continues to be mired in legal tangles as the government is slated to file for a fresh petition in the High Court.

Uppal depot as the site has been renamed has also caused some unexpected trouble to the Hyderabad Metro Rail (HMR) as it had to face dredging of the Hyderabad nala flowing into the Musi River. The nala got clogged due to dumping of debris, industrial waste, garbage and other sundry things over the years.

Danger of flooding

Senior officials realised that unless the drain was thoroughly dredged there was a real danger of flooding of the depot during heavy inflows. The work was taken up along with laying slabs on the drains, widening road and shift of transmission lines as well as poles in the area.

Cantonment land

Another pending issue of getting permission of the Defence Ministry for the Cantonment land for the Line Two – Jubilee Bus Station (JBS) to Falaknuma -- is on the way towards a solution with the HMR offering 25 acres at Jawaharnagar in exchange for the three acres – two at Parade Grounds for an overhead station for Line Three – Nagole to Shilparamam -- and one acre at JBS for the terminal station.

Price

HMR Managing Director N.V.S. Reddy said that a price of Rs.17.21 crore was calculated for the three acres at Rs.5.73 crore an acre and equivalent value of land of 25 acres was shown by the Ranga Reddy Collectorate. The file is under circulation.

The National Highways Authority of India (NHAI) which has finally agreed to allow the elevated project to be built on the central media for Line One – L.B.Nagar to Miyapur, is to call for tenders soon. The Rs. 32-crore work (Rs.16 crore each) is to lay additional lanes from – Miyapur to Balanagar and L.B.Nagar to Mahabub Mansion, each stretch is about 10-12 km length.

0 / 0
Sign in to unlock member-only benefits!
  • Access 10 free stories every month
  • Save stories to read later
  • Access to comment on every story
  • Sign-up/manage your newsletter subscriptions with a single click
  • Get notified by email for early access to discounts & offers on our products
Sign in

Comments

Comments have to be in English, and in full sentences. They cannot be abusive or personal. Please abide by our community guidelines for posting your comments.

We have migrated to a new commenting platform. If you are already a registered user of The Hindu and logged in, you may continue to engage with our articles. If you do not have an account please register and login to post comments. Users can access their older comments by logging into their accounts on Vuukle.